Filed under: Press Releases 2019

Supreme Court Ruling technical in nature and does not change any of the issues for Eirgrid and their partners ESB

The critical issue of access to landowners’ property could not be assessed because access routes were never submitted for approval to An Bord Pleanála.

Continue February 20, 2019

North-South Interconnector planning approval quashed in Northern Ireland

The approval for the North-South Interconnector in Northern Ireland was quashed today at Belfast High Court, at the behest of the Department for Infrastructure in Northern Ireland. This is a golden opportunity for Government to adopt a policy of undergrounding if they want this ‘critical infrastructure’ ever to be established.

Continue February 9, 2019

North-South Interconnector: NEPPC calls on Commission for Regulation of Utilities and on European Commission to investigate unauthorised interference and non-compliance with the planning conditions.

Request for Eirgrid also to be investigated for facilitating ESB ownership of discharge of planning conditions .

Continue February 6, 2019

ESB proposals to blatantly breach planning conditions and ignore basic landowner rights demands Government action.

Unacceptable proposals unfairly put Local Authorities on front line for a project they never approved.

Continue February 6, 2019


NEPP on Facebook

About NEPP

NEPP is the overall representative group for the people of Ireland's North East who advocate that high power electric cables should go underground.

Register for Cycling Challenge

Sections

Sign the Petition

Press Releases

Donate

PayPal donations are for small amounts only. Please lodge larger amounts directly to our AIB Bank Acc.

Recent Posts

Archived Sections